HIGH SCHOOL
The High School now has all of the heating and cooling
units that kept us from placing a roof on the building. The parts
have been lowered through the roof opening and we can now place decking
and roof materials to enclose the building. Temporary heat is being
set up so that our craftsmen can begin the interior work.
Our color selection revolves around school colors.
The gym should have school color mats with a falcon and the floor will
have falcons painted on both sides. Physical education locker rooms
and team rooms will have red lockers. The team rooms should have
larger lockers to help contain uniforms, etc.
We will have an equipped stage in the Auditeria, but this
area will be too small for larger audiences so I have requested that the
Ohio School Facilities Commission allow us to equip a stage in the gym.
We have designed an area at the East end of the gym that could house a
stage so with available project funds, we could develop a stage for having
several of our larger audience productions there such as graduation, elementary
musicals, high school productions, homecoming, etc.
We are still looking at an August opening at this time.
MIDDLE/PRIMARY SCHOOL
The design development phase is being completed and early
work to route temporary computer lines, etc. will take place this summer.