Building Update
from
Dr. Meade


August 31, 2000


The high school project is close to 500 days without a loss of time accident.  The air conditioning is on the entire building.  The floor will be installed in the gym beginning September 5th.  Kitchen equipment will be installed within the next two weeks.  Work on the parking lots and roads continues--using the lime stabilization process to make the ground solid.  Loose equipment and hardscape/landscape contracts were awarded.  Cabinetry is being installed in each classroom and ceiling tile will be starting to be installed soon.  We hope to begin moving items over to the school in November and December.  Students should begin at the new high school when they return from Christmas Break.  We will try to avoid bad weather when scheduling the dedication and open house.