The High School is still on schedule with the
heating units to be shipped November 23rd and the heat recovery wheels
on December 15th. Roofing may be delayed due to having to place these
items throughout the opening before enclosing the school.
Other items include:
The second floor walls are starting to go up and the floors
have been poured. We are moving initial build up of the East Parking
lot to now and will cover the lot with the first asphalt base.
We have issues with delays on computer drops being placed
in each classroom. We have said that we wanted these but the delays
have made it more expensive. A lightening package has also been delayed
in being considered and has become more expensive.
On the Middle/Primary school project, we have the design
approved by the Board and are looking at the first specifications.