Building Update
from
Dr. Meade


October 16, 2000


The wood floor of the gym is now installed and is being sanded.  Bleachers are scheduled to be installed.  The lime stabilization of the soil of the parking lot and roads should be completed by this Friday, October 13. Sidewalks and curbs are being poured and top soil is being spread.  Finishes on walls and floors continue to be completed.  Loose equipment contracts have been awarded with a completion date of December 8, 2000.  A wastewater treatment plant pre-construction meeting was held on October 11.  Work will begin October 23 with over eighty truckloads of pre-cast concrete parts arriving to build the plant.  The Phase II Middle/Primary School will have a construction document review on October 19.

An auction will be scheduled for surplus educational equipment and fixtures of the current high school.
 
 

Click here to see more photos