Building Update
from
Dr. Meade
October 16, 2000
The wood floor of the gym is now installed and is being
sanded. Bleachers are scheduled to be installed. The lime stabilization
of the soil of the parking lot and roads should be completed by this Friday,
October 13. Sidewalks and curbs are being poured and top soil is being
spread. Finishes on walls and floors continue to be completed.
Loose equipment contracts have been awarded with a completion date of December
8, 2000. A wastewater treatment plant pre-construction meeting was
held on October 11. Work will begin October 23 with over eighty truckloads
of pre-cast concrete parts arriving to build the plant. The Phase
II Middle/Primary School will have a construction document review on October
19.
An auction will be scheduled for surplus educational equipment
and fixtures of the current high school.